After supporting the existing floors, the Greco group, cut the double brick walls in specific areas to install more jack posts. The beam to be installed is about 600 pounds and is over 15 feet long. It is supported on one side by a steel post and on the other by the former chimney which is to be filled with concrete to create a pillar. The next day the men came back and installed the beam by first lifting onto scaffolding, and then sliding it into the “pocket”. Following that, they filled the gap above the beam and the brick wall above. Then they demolished the brick wall below and voila, our house was open to the elements. The next day they completed the job by making a 6 foot wide opening in the rear of the basement between the old house and the new.
Last item was the installation of the steel pole. Imar Steel sent over the welder with the post and he installed it in no time. For us this was a major hurdle and we are very glad it is behind us.