Oh No, Don't Let the Rain come in....

The forms were removed the day after the concrete was poured and a few days later the process of waterproofing the foundation began. On day one, Nuno and Vera sprayed on a latex based product to seal the exterior concrete. On day two, they applied the 2-ply membrane to the walls with special fasteners. Once the backfilling is completed around the outside of the foundation the pressure of the soil will complete the process of sealing the membrane to the wall. We anticipate that we will never have any water leakage issues with this system. According to Nuno, "this is as good as it gets!"



Friday, July 10, 2009

It's All In Your Form!

Today, the guys from Chico's Forming installed the 8 foot forms for the poured concrete foundation walls. The walls once poured, will be 10" wide and 8 feet 1 inch above the footings. Rob, Marco and Bruno got the forms up in no time. Monday we pour concrete!

Friday, July 3, 2009

Solid Footing!

On Thursday July 2nd, our forming contractor (Chico’s Forming) came in and poured concrete into the forms for the footings for the exterior walls of the house. They used a special concrete truck with a conveyor belt type device to move the concrete from the truck to the rear of the house, where they then filled wheelbarrows and poured the footings. Steel rebar was placed in the poured footings where they will tie into the bench footing. Next week they are supposed to come back, erect the forms for the walls and pour the walls and the bench footing at the same time.